WEST POINT -- The city and UDOT entered into a safe sidewalk project cooperative agreement on Tuesday.

The city was awarded a grant for a sidewalk project along the south side of 300 North. The sidewalk will run from 1795 West to 1885 West. The total cost of the project is expected to be around $47,000.

UDOT will fund 75 percent of the project and the city will contribute 25 percent. Any utility relocation will be paid equally between by the city and utility company. No relocation is expected with this project, but the note is included for clarity. Construction must begin within one year of the date of the agreement.