Utility substation funding approved

Thursday , October 11, 2012 - 2:04 PM

STAFF AND CORRESPONDENTS

Staff And Correspondents

BOUNTIFUL -- City leaders have approved funding for ongoing work at a utility substation, which feeds power to the Bountiful City Light & Power Company.

City council members approved an expenditure of $267,256 to upgrade the 138 kV Substation, located near Legacy Highway in Centerville, as part of phase 3 of the project.

The work will include removal of the existing structure and installation of a new 138kV structure, breakers, and switches from the interconnection from the PacifiCorp substation to the BCL&P power transformer.

Cache Valley Electric is the contractor who was awarded the project.