Local News
Ogden City gives briefing on status of water line replacement across exposed Pineview Reservoir lake bed
PINEVIEW RESERVOIR — Ogden City officials are updating the public on a major infrastructure project that's created quite the striking visual. With water drawn down at Pineview Reservoir, crews have begun work on a phase of the $100 million replacement of the city's 36-inch water transmission line across the lakebed of the reservoir that officials hope to wrap up by year's end. On Friday, Ogden City Public Services Executive Director Justin Anderson addressed local media at the Port Ramp Marina about the project and what is planned for the coming months. "Today we're up here to talk ...